Third Expansion of the Holy Haram – Makkah
Project Overview
Eco Vista executed earthworks, excavation, side support works, and dewatering systems for the third expansion of the Holy Haram and its surrounding areas in Makkah.
The project was delivered in coordination with leading contractors and consultants, ensuring strict compliance with safety, quality, and engineering standards.
Client’s Challenge
The project required execution in a highly sensitive location with strict safety and environmental controls, limited space, and deep excavation works.
Our Solution
Eco Vista implemented a controlled shoring and dewatering system using soldier piles, ensuring site stability, safety, and efficient execution within the project timeline.
Project Preview
Saudi Binladin Group
Dar Al-Handasah
Shoring System
170 m
9.5 m
50 Days