Third Expansion of the Holy Haram – Al Anqari Site

Earthworks, Excavation, Side Support Works & Dewatering Systems

Third Expansion of the Holy Haram – Al Anqari Site

Project Overview

Eco Vista General Contracting Co. executed comprehensive earthworks, excavation, side support works, and dewatering systems for the third expansion of the Holy Haram at Al Anqari Site in Makkah.

The project was delivered in a highly sensitive and densely built environment, requiring precise engineering coordination, advanced shoring systems, and strict adherence to safety and quality standards.

Engineering Challenges

The project involved deep excavation works within a limited space and close proximity to existing structures. Maintaining ground stability and controlling groundwater levels were critical to ensure safe execution.

Our Solution

Eco Vista implemented a controlled soldier pile shoring system combined with efficient dewatering solutions. This approach ensured excavation stability, protected surrounding structures, and enabled smooth progress within the project timeline.

Project Preview

Saudi Binladin Group
Dar Al-Handasah
Shoring System
445 m
5.0 m to 9.2 m
Soldier Piles
50 Days

Don’t hesitate to contact us

Call us
+ 966 50100 9092
Email us
info@ecovista.com
Chat with us
Select the fields to be shown. Others will be hidden. Drag and drop to rearrange the order.
  • Image
  • SKU
  • Rating
  • Price
  • Stock
  • Availability
  • Add to cart
  • Description
  • Content
  • Weight
  • Dimensions
  • Additional information
Click outside to hide the comparison bar
Compare