Project Overview
Eco Vista General Contracting Co. executed foundation works, earthworks, excavation, side support works, and dewatering systems as part of the third expansion of the Holy Haram at Al Tawheed Site in Makkah.
The project required advanced engineering solutions due to deep excavation levels, proximity to existing structures, and the need for continuous groundwater control, all within a highly sensitive and active area.
Engineering Challenges
The project involved deep foundation and excavation works adjacent to existing structures and infrastructure. Maintaining excavation stability and controlling groundwater levels were critical throughout execution.
Our Solution
Eco Vista implemented a robust soldier pile shoring system combined with efficient dewatering solutions. This approach ensured excavation safety, structural stability, and uninterrupted project progress while meeting strict safety and quality requirements.